Monday, 19 December 2011

Great Western Mainline Electrification Project - Structural Clearances

Great Western Mainline Electrification Project - Clearance for 150 Structures
Is it going to fit?

Severn Partnership has been assisting a major engineering consultancy in answering this question for 150 Structures on the Great Western Mainline as part of the Great Western Electrification Project.
Severn Partnership High Accuracy Railway Surveying

Severn Partnership Surveyors have been producing Topographical Surveys to establish Clearances for blacklisted structures and provide sufficient information surrounding the structure to allow for alteration proposals.

The 8 month long project, which ran on time saw at its peak up to 10 structures surveyed in a single night shift.

There were no incidents and Severn ensured that all the data was to the highest Quality, measured Safely and Delivered Professionally on Time.

For more information on our high accuracy railway surveys or to discuss your project requirements further please email: webenquiry@severnpartnership.co.uk or contact Anett Dude on 0844 880 8247 
Topographical Surveys for Structural Clearance Analysis

Monday, 12 December 2011

Track Renewals - Track Alignment & Cess Detail Surveying

High Accuracy Track Alignment & Cess Detail Surveying
With the continuous need to replace rail track, the Renewal train has played a vital role in delivering this rapid renewal system.  Working alongside this, Severn has provided the high accuracy survey data critical to its continuing success.

Track Renewal Train - Railway Surveying
Recently Severn have completed over 80,975 yards (approx. 46 miles) of topographical track alignment and cess detail survey along a section of the busy WCML LNW Route.  This work produced 30 digital survey models in both MX Genio and AutoCAD formats and 373 separate SC0 files for ClearRoute Gauging Analysis.

80% of the work was carried out in a Green Zone working environment, utilising both midweek night line blockages and weekend T3 possessions.  All the work was produced to the highest quality standards and delivered professionally on time. 

For more information on our high accuracy railway surveys or to discuss your project requirements further please email: webenquiry@severnpartnership.co.uk or contact Jamie Price on 0844 880 8247  

Monday, 5 December 2011

Crossrail High Accuracy Surveying for Tunneling Monitoring

Crossrail Amberg Kinematic Laser Scan Point Cloud - Track
 As the Crossrail project starts it’s tunneling under the streets and infrastructure of London a huge amount of preparation work is going on to prevent monitor and  subsidence. 

Crossrail Amberg Kinematic Laser Scan Point Cloud - Paddington
Tunneling has already begun from the Western Portal, just outside Paddington Station, where The Severn Partnership has been busy compiling a comprehensive data set to be used for the monitoring of Network Rail infrastructure as the huge Tunnel Boring Machines (TBMs) munch their way underneath. 


Crossrail Paddington P-way Track Survey
Combining High Accuracy Leica TS30, 0.5 arc second 0.5mm, Total Stations with the latest Amberg Track Geometry Measuring Devices to coordinate every track and cross over unit on the approach to Paddington Station has provided the Crossrail team with a benchmark survey to monitor changes against. In addition a Kinematic Laser Scan Point Cloud provides a 3 dimensional model of all overhead line equipment and gantry structures prior to the TBMs passing underneath. Should any movement occur during tunneling, the entire stretch of track and infrastructure can be precisely reinstated with confidence. If all goes to plan, no one will even know the machines have been there....


For more information or to discuss your project requirements further please email: webenquiry@severnpartnership.co.uk or contact Rollo Rigby on 0844 880 8247  

Tuesday, 8 February 2011

Real time monitoring for track movement 24/7

Severn Partnership was approached by Alun Griffiths (Contractors) Ltd. to offer a
proposal for the monitoring of rails, for movement, during the piling works for a new footbridge adjacent to the railway fence-line.

The proposal needed to adhere to Network Rail Standard NR/BS/LI/045 ‘Monitoring track over or adjacent to Civil Engineering works: procedure and intervention levels.’

The extent of the monitoring, covered 90m of track length over four rails, with prisms located at 3m centres (124 prisms in total).  Readings being taken 24 hours a day, 7 days a week - feeding back data over an Internet link to our office.

Benefits of Automated technique:
  • Minimised on site manpower (security guard only required)
  • Cheaper overall than manned monitoring
  • Real time results, with reports on twist, CANT, gauge & movement
  • Client reports on demand
  • Piece of mind !
24/7 observations - unmanned
3d monitoring control station


Call Nick Blenkarn or Bob Hutchings at Severn Partnership to discuss your track monitoring requirements.

Contact Us

Tuesday, 1 February 2011

Railway Track survey and GPS Control - A frosty start to 2011

Severn Partnership has had to come out “the blocks” at an electrifying pace in 2011 with over 70 miles of mainline railway already surveyed.

Railway surveyors on track in the snow

Railway Track surveys included:

  • St. Pancras to Sheffield  – Midland Mainline over 48 Miles of track surveyed making also making use of the GRP5000 kinematic laser scanning system wit the latest clearoute software from Amberg Technologies.
  • Walsall to Rugeley Trent Valley – RRN – 12 Miles of railway track including fence to boundary fence for the West Midlands Signalling Renewals.

Quality survey data is being delivered to the clients using Severn Partnership’s experienced railway surveyors who are all PTS qualified with Senior Surveyors being COSS qualified.

Large scale geodetic networks are observed using upto 16 number GPS units, simultaneously at times. This is backed up by bespoke Railgrid software experience in which has been gathered over the last 7 years and the commissioning of 9 Railgrid mapping projections including the MM07 Snakegrid for Midland Mainline in 2007.