Great Western Mainline Electrification Project - Clearance for 150 Structures |
Is it going to fit?
Severn Partnership has been assisting a major engineering consultancy in answering this question for 150 Structures on the Great Western Mainline as part of the Great Western Electrification Project.
Severn Partnership High Accuracy Railway Surveying |
Severn Partnership Surveyors have been producing Topographical Surveys to establish Clearances for blacklisted structures and provide sufficient information surrounding the structure to allow for alteration proposals.
The 8 month long project, which ran on time saw at its peak up to 10 structures surveyed in a single night shift.
There were no incidents and Severn ensured that all the data was to the highest Quality, measured Safely and Delivered Professionally on Time.