Monday 19 December 2011

Great Western Mainline Electrification Project - Structural Clearances

Great Western Mainline Electrification Project - Clearance for 150 Structures
Is it going to fit?

Severn Partnership has been assisting a major engineering consultancy in answering this question for 150 Structures on the Great Western Mainline as part of the Great Western Electrification Project.
Severn Partnership High Accuracy Railway Surveying

Severn Partnership Surveyors have been producing Topographical Surveys to establish Clearances for blacklisted structures and provide sufficient information surrounding the structure to allow for alteration proposals.

The 8 month long project, which ran on time saw at its peak up to 10 structures surveyed in a single night shift.

There were no incidents and Severn ensured that all the data was to the highest Quality, measured Safely and Delivered Professionally on Time.

For more information on our high accuracy railway surveys or to discuss your project requirements further please email: webenquiry@severnpartnership.co.uk or contact Anett Dude on 0844 880 8247 
Topographical Surveys for Structural Clearance Analysis